Latest News

Trusses for new truss factory
27/11/2018

Trusses for new truss factory

The roof trusses for the front office – made in our factory at Hemingstone - are in place, ready for the roof cladding. Click here to read more

Ready for the rain
15/10/2018

Ready for the rain

The roof is on and with rapid progress on the blockwork and cladding, the main section of our new factory will soon be weatherproof. Click here to read more

New factory takes shape
31/08/2018

New factory takes shape

The steel framework for our new factory is progressing quickly. Click here to read more

Factory floor is a mega pour
22/06/2018

Factory floor is a mega pour

Work on our new factory beside the A14 at Claydon is continuing on schedule. A matrix of steel mesh has been formed above the piles to reinforce a 300 mm thick concrete floor slab and the slab has been created in three stages, using pumped concrete. Click here to read more

New factory construction underway
11/04/2018

New factory construction underway

Groundwork has begun on our new factory at Claydon. Click here to read more

Easy flooring solution for new business centre
08/09/2015

Easy flooring solution for new business centre

A new business centre near Colchester has made good use of metal-web joists in the latest phase of steel-framed buildings. Click here to read more